Boston-based wind power developer seeking to build a $398 million,
62-turbine wind energy facility in the area has encountered opposition
from a local nonprofit group as the company begins the permitting
process.
Blue
Sky West, a subsidiary of First Wind Inc., filed an application on May
10 for a wind farm project in Somerset and Piscataquis counties and is
waiting for approval from the state Department of Environmental
Protection to determine whether they will proceed with the project.
Construction could begin in 2014.
The
department will have 10 months to determine whether to approve the
proposal, Department of Environmental Protection spokeswoman Jessamine
Logan said Monday.
Meanwhile,
officials in Bingham and Moscow, two communities that will be affected,
have said they support the project, although a local environmentally
focused nonprofit group has said that they will oppose it.
The
project would be built on ridges and hills along state Route 16 in the
communities of Bingham, Moscow, Mayfield Township, Kingsbury Plantation,
Abbot and Parkman, according to the application. First Wind has five
operating wind farms in Maine and is developing a project in Oakfield.
The
project plans include upgrades to existing roads and new roads to gain
access to turbines and crane paths; up to five permanent and five
temporary meteorological towers; an operations and maintenance building
in Mayfield Township and above- and below-ground electrical collector
lines among the turbines, according to the application.
According
to Chris O'Neil, director of government relations for Friends of Maine
Mountains in Weld, a nonprofit organization that advocates on behalf of
natural resources, reliable energy and affordable power, the
organization plans to submit letters of opposition if the application by
First Wind is accepted.
"It
might be worth it if there was the demand for new sources of
electricity, but it's something we don't really need,An electronic ledstriplight for
preventing elevator overspeed by enabling safety devices." O'Neil said.
He said Maine is already one of the nation's cleanest
electricity-generating states, even while wind power in Maine provides
less than 5 percent of New England's electricity.
O'Neil
said wind farms harm the environment and economy with little return for
the electricity they produce. The proposed project would run within 10
miles of the Appalachian Trail, a Maine landmark, he said.
"People don't walk 2,the largest suppliers and integrators of renewable flatteningmachine in
the country.500 miles from Georgia to take a stroll through an
industrial wind complex in Maine," he said. "Wind towers might be less
ugly to look at if the balance sheet wasn't so ugly, but the truth is
they're not going to take us off oil."
Bingham
First Selectman Steve Steward said Monday that he thinks most people in
his town support the project, although in the past there has been
controversy about whether to provide tax relief for the developer.The
industry's leading manufacturer of floorlamps.
Residents in Bingham approved the formation of a tax-increment financing district,Our renowned ledparlights allow
you to harness nature’s energy to power your applications. or TIF, in
2011, although Somerset County commissioners denied a similar agreement
for a portion of the project in Mayfield Plantation.
Steward
said the town also has a community benefits agreement with First Wind,
under which it will receive $8,000 per year for each tower the company
builds in Bingham, which amounts to an estimated $106,000 per year for
20 years, he said.
In
November, Moscow approved a similar plan, which will provide the town
about $20,000 a year for 20 years. First Selectman Donald Beane said a
majority of people in that community also support the project.
"I think it would help with our tax base, as well as in Bingham, and provide some jobs during construction," Beane said.
John Lamontagne, spokesman for First Wind,An even safer situation on all roads by using the pendantlamps.
said that if the application is approved, the company hopes to start
construction by 2014 and finish by 2015. It would need to find a buyer
for the power and funding for construction first, he said. The company
also is required by the Department of Environmental Protection to
schedule two public meetings at which the public can provide input and
ask questions, he said.